Which document along with the initial capabilities document guides the material solution analysis and technology maturation and risk reduction phases?

Recommended textbook solutions

Which document along with the initial capabilities document guides the material solution analysis and technology maturation and risk reduction phases?

Elementary Number Theory

7th EditionDavid Burton

776 solutions

Which document along with the initial capabilities document guides the material solution analysis and technology maturation and risk reduction phases?

Book of Proof

2nd EditionRichard Hammack

340 solutions

Which document along with the initial capabilities document guides the material solution analysis and technology maturation and risk reduction phases?

Numerical Analysis

9th EditionJ. Douglas Faires, Richard L. Burden

873 solutions

Which document along with the initial capabilities document guides the material solution analysis and technology maturation and risk reduction phases?

Numerical Analysis

8th EditionJ. Douglas Faires, Richard L. Burden

775 solutions

Home

Subjects

Expert solutions

Create

Log in

Sign up

Upgrade to remove ads

Only SGD 41.99/year

  • Flashcards

  • Learn

  • Test

  • Match

  • Flashcards

  • Learn

  • Test

  • Match

Terms in this set (53)

Which of the following are purposes of the Defense Acquisition System?

A. Develop technology
B. Produce weapons system.
C. Provide logistics support.

Documents produced during the JCIDS process are used to support Defense Acquisition System milestone decisions?

True

Which of the following are characteristics of the Material Solution Analysis phase?

a. The AoA is conducted.
b. A PM is selected and a program office is established.
c. Promising technologies are analyzed to determined which one is best suited to meet validated requirements.

The results of the basis for which of following?

Acquisition Strategy.

Which one of the following is considered a primary goal of an Acquisition Strategy?

Minimize the time and cost needed to satisfy validated needs.

Which term is defined as the minimum acceptable value for the performance that is necessary to satisfy an identified need?

Threshold.

Which of the following are considered parameters of the Acquisition Program Baseline? Select all that apply.

a. Cost
b. Performance.
c. Schedule.

A successful Milestone A decision leads to entry into which phase?

Technology Maturation and Risk reduction.

The AS must be approved by the MDA prior to what?

Release of a formal solicitation.

The MDA must approve which of the following for a program to successfully complete Milestone A? (Select All the apply).
.

a. The proposed material solution.
b. The Acquisition Strategy.
c. A life Cycle Sustainment Plan

When does a program enter the TMRR phase?

When the AoA has been completed and the MDA has approved the AS.

Which of the following are goals of the TMRR phase? (Select all that apply)

a. Reduce technology risk.
b. Demonstrate critical technologies through prototyping.
c. Conduct a preliminary design review.

True or False? One of the requirements for a project to exit the TMRR phase is that the technology has been demonstrated in a relevant environment.

True

What is the purpose of Milestone B?

Initiate engineering and manufacturing development.

Which of the following are key considerations of the EMD phase? (Select all that apply)

a. Completes all needed hardware and software detailed design.
b. Systemically retires any open risks.
c. Prepares for production and deployment.

Which of the following is a responsibility of the PM during EMD phase?

Finalizing designs of the product support elements

Which of the following are considerations for Milestone C? (Select all that apply).

a. Cost estimates.
b. Environmental issues.
c. Manpower estimates.

True or False? An updated Acquisition Program Baseline is required for Milestone C approval.

True.

MDA decisions made during the Production and deployment phase are documented where?

Acquisition Decision Memorandum.

True or False? Acquisition programs enter the Full Rate Production and Deployment after completing the Life Cycle Sustainment Plan.

False

The Operations and Support phase is based in what?

An MDA-approved LCSP.

True or False? PMs are encouraged but not required to establish organic depot maintenance capabilities?

False.

Which of the following are PM considerations during the Disposal? (Select all that apply).

a. Complete reuse or recycling of system components and materials.
b. Waste disposal.
c. Sale or donation to the private sector or other governments.

Which of the following are key considerations of Low Rate Initial Production? (Select all that apply).

a. Establishes an initial production base for the system.
b. Provides OT&E test articles.
c. Provides an efficient ramp-up to full rate.

Defense Acquisition System (DAS) uses "Milestones" to oversee and manage acquisition programs. True or False?

True.

How many "Milestones" they are?

Three: A, B, & C.

What are the names of the "Milestones?"

1. Milestone "A: Initiates Technology Maturation and Risk Reduction phase (TMRR).
2. Milestone "B: initiates Engineering and Manufacturing Development phase (EMD).
3. Milestone C: Initiates Production and Deployment phase (PD).

The Defense Acquisition System is governed by?

a. DoDD 5000.01

b. DoDI 5000.02

A favorable Milestone C decision authorizes entry to this phase.

What is production and development?

This is a true statement about the Acquisition Program Baseline (ABP)?

What is the PM, in coordination with the user, prepares the APB at program initiation?

The Acquisition strategy defines the increment about to be undertaken, as well as subsequent increments in this requirement.

What is the time-phased needs?

This is used to create the Acquisition Program Baseline (ABP).

What is the Defense Acquisition Management Information Retrieval (DAMIR)?

This person prepares the Acquisition Strategy during the MSA.

Who is the Program Manager?

Prepared at program initiation and revised to subsequent milestone reviews, program, restructuring, or unrecoverable deviations.

What is the APB?

During this phase, the appropriate operational authority will declare Initial Operational Capability (IOC) when the defined operational organization has been equipped and trained, and is determined to be capable of conducting missing operations.

What is the Production and Deployment phase?

The acquisition document that states each PM must prepare and the MDA must approve an Acquisition Strategy (AS).

What is the DoDI 5000.02?

This is the agreement between the MDA and Program Manager that will be used for tracking a program.

What is the Acquisition Program Baseline?

The Operations and Support Phase begins after the production or deployment decision and is based on which Milestone Decision Authority (MDA) approved document?

Life Cycle Sustainment Plan (LCSP).

What is the purpose of an Acquisition Strategy (AS)?

a. To guide execution from initiation through re-procurement of systems, subsystems, components, spares, and services beyond the initial production contract award and during post-production support.

Before a project enters the TMRR phase, the AoA must be complete and the Acquisition Strategy (AS) is approved by the MDA.

True

When is the Acquisition Program baseline (APB) prepared?

Prepared at program initiation and revised to subsequent milestone reviews, program restructuring, or unrecoverable deviations.

What authorizes entry into the Engineering and Manufacturing Development (EMD) phase?

Milestone B decision.

What authorizes entry into the Production and Deployment phase?

Life Cycle Sustainment Plan (LCSP)

DoD defines and validates requirements through the Joint Capabilities Integration and Development System (JCIDS) and develops technology, produces weapons systems, and provides logistics support through the Defense Acquisition System.

True.

The Materiel Solution Analysis Phase (MSA) ends when the Analysis of Alternatives (AoA) has been completed, a materiel solution option for the capability need is recommended, and the phase-specific entrance criteria for the initial review milestone have been satisfied.

True.

In order for the Program Manager to maximize affordability from program initiation through post-production, the Acquisition Strategy must evolve and become increasingly more definitive.

True.

What authorizes entry into the Production and Deployment phase?

Milestone C decision.

What authorizes entry into the Engineering and Manufacturing Development (EMD) phase?

Milestone B decision.

In what document does the Program Manager (PM) address the demilitarization and disposal requirements?

Life Cycle Sustainment Plan (LCSP).

What is the purpose of an Acquisition Strategy (AS)?

To guide execution from initiation through re-procurement of systems, subsystems, components, spares, and services beyond the initial production contract award and during post-production support.

What are two outputs of the Technology Maturation and Risk Reduction (TMRR) phase?

a. Capability Development Document (CDD) and Reliability, Availability, and Maintainability Cost Report (RAM_C).

The key activity during the Materiel Solution Analysis Phase (MSA) is to analyze promising technologies to determine which one is best suited to meet the validated requirement.

True.

Which is used to create the Acquisition Program Baseline (APB)?

Defense Acquisition Management Information Retrieval (DAMIR).

Sets with similar terms

ACQ 101

83 terms

staycalmandloveblue

Module 4

40 terms

RobertWallace

ACQ 101

75 terms

banabb89

Week 2 FM in Acquisitions

47 terms

Doug_Fletcher8

Sets found in the same folder

Acq 101 -Mod 4

41 terms

Ericka_Kadner

Acq 101 - Mod 3

30 terms

Ericka_Kadner

ACQ 101 Module 7 Financial Management

41 terms

leroyday40

ACQ 101 Module 13 Life Cycle Logistics

45 terms

leroyday40

Other sets by this creator

ACQ 0040

7 terms

staycalmandloveblue

Combating Trafficking In Person (CTIP) 2022

22 terms

staycalmandloveblue

DoD Mandatory Controlled Unclassified Information…

20 terms

staycalmandloveblue

ALL HAZARDS AWARENESS

10 terms

staycalmandloveblue

Recommended textbook solutions

Which document along with the initial capabilities document guides the material solution analysis and technology maturation and risk reduction phases?

Operations Management: Sustainability and Supply Chain Management

12th EditionBarry Render, Chuck Munson, Jay Heizer

1,698 solutions

Which document along with the initial capabilities document guides the material solution analysis and technology maturation and risk reduction phases?

Information Technology Project Management: Providing Measurable Organizational Value

5th EditionJack T. Marchewka

346 solutions

Which document along with the initial capabilities document guides the material solution analysis and technology maturation and risk reduction phases?

Operations Management: Sustainability and Supply Chain Management

12th EditionBarry Render, Chuck Munson, Jay Heizer

1,698 solutions

Which document along with the initial capabilities document guides the material solution analysis and technology maturation and risk reduction phases?

Information Technology Project Management: Providing Measurable Organizational Value

5th EditionJack T. Marchewka

346 solutions

Other Quizlet sets

Psychopathology Midterm

185 terms

Grac372PLUS

Commercial Transactions - Ex2.2 - Requirements for…

21 terms

jkastne

Clin Med and Pharm Exam 1

76 terms

knispelm

CMI final

34 terms

ggold4

Related questions

QUESTION

Two special reasons why teams are special

2 answers

QUESTION

This type of change involves introducing a practice that is new the industry.

3 answers

QUESTION

Why do movie theaters sell tickets for an afternoon showing of a movie at a lower price than the 7 p.m. showing of the same movie?

15 answers

QUESTION

Prior to beginning make your assessment make sure to address and provide appropriate care of what?

15 answers

What is initial capabilities document?

The ICD quantifies needed capability requirements and gaps associated with operational risks across the joint force. It also proposes materiel and/or non-materiel approaches to closing or mitigating some or all of those identified capability gaps.

What is the capability development document?

Capability Development Document (CDD) The Capability Development Document (CDD) specifies the operational requirements for the system that will deliver the capability that meets the operational performance criteria specified in the Initial Capabilities Document (ICD).

What document is prepared by the user to document a need that requires a material solution?

– If a materiel solution is proposed, an Initial Capabilities Document (ICD) is developed.

What document S are created and approved in the JCIDS process and required for a program to enter into and progress through the DAS?

The three categories of capability requirement documents specified by the JCIDS are: Initial Capabilities Document (ICD) (including Information Systems Initial Capabilities Document (IS-ICD)) Capability Development Document (CCD) (including Information Systems Capability Development Document (IS-CDD))